Aug 14, 2026 earnings call — Transition to AI compute and Columbiana data center
Company reported revenues of $6.6 million and first GPU revenue of $1.1 million, with positive adjusted EBITDA of $3.3 million.
Revenue $0.0B (est $0.0B) · EPS $-0.17 (est $-0.05)
Key quotes
"At the Colombiana, Alabama, AI campus, the company is still targeting Phase 1 ready for service in December of 2026 and Phase 2 in end of Q1 2027."
"GPU revenue recognized for $1.1 million, representing the company's first GPU bare-metal rental initial fleet of B200 and B300 GPUs deployed at the Columbiana, Alabama facility and it was started a little bit third week of May to the end of June."
"The company is currently in advanced debt financing discussions for the Alabama data center to advance our path to growth and mitigate dilution."